| Timeline for
Milestones |
| |
| Fall 2006 |
 |
Vegetation sampling (biomass, biodiversity) of diked and undiked
marshes. |
 |
Project modeling team meets at Sapelo Island to discuss model
refinements and scaling issues. |
|
| |
| Winter 2006/2007 |
 |
Field research team meets at
Athens GA to discuss analysis/results and identify data gaps. |
 |
SLAMM model development for key river-dominated estuaries of the South Atlantic (GA-SC) coast. |
|
| |
| Spring 2007 |
 |
Submit year 2 annual report to
EPA. |
 |
Analysis and synthesis of field data. |
 |
SLAMM model development for estuarine and non-estuarine wetlands of the South Atlantic coast. |
|
| |
| Summer 2007 |
-
Final SLAMM modeling for entire South Atlantic coast, and GIS-based
scaling of ecosystem services.
-
Fill missing data gaps, data synthesis.
-
Disseminate research findings at professional and public meetings.
|
| |
| Fall 2007 |
|
|
| |
| Winter 2007/2008 |
|
|
| |
|